A second year for 22 operators: extending permits without missing a single window

A roofing materials plant in the Poltava region decided to keep all the operators from India we had brought in two waves for a second year. We walk through our part of the work: how we checked documents for twenty-two people, why we file on the first day of the window, what the transfer of two operators changed, how a new dormitory affected registration, and how twenty-two people applied for residence permits without queues.

  • 22 workerstwo waves a month apart, one-year permits
  • 50-20 daysthe window to apply for an extension before the permit ends
  • up to 3 daysworking days for a decision on an extension or update
  • 0 refusalsevery application filed in the first week of the window

Typical scenario. This story is built from situations common in our work with foreign workers. The company, people and figures are illustrative. It is not a report on completed work but a walk-through of how WORKIN runs such a project from request to handing people over to the shift.

Illustrative photo. The company and workers in the story are fictional.

اپ ڈیٹ: 14 ستمبر، 202610 min readWORKIN editorial

Brief dossier

Client
Roofing materials plant: metal roof tiles and profiled sheeting
Region
Poltava region
Workers
22 line operators, packers and slingers from India
Permits
One year, two waves a month apart
What WORKIN did
Date register, extensions, permit updates, address documents, residence permit filings
Focus
Extending documents for two waves into a second year

01 / The decision

The plant keeps everyone, and more has changed in a year than it seems

A year ago we brought twenty-two workers from India to the plant: profiling line operators, packers and slingers. The first wave of fourteen arrived a month before the second wave of eight, so their permits also end a month apart. In August the HR director wrote to us briefly: the plant wants to keep everyone for a second year.

For the plant it's one decision. For us it's twenty-two sets of documents, any of which could have changed over the year. Nataliia, head of our documents department, started not with applications but with an inventory: what's currently in each person's permit, contract, passport and residence permit.

We keep the control-date register from day one of every project, so the permit end dates were known well in advance. But the register shows dates, not the changes that have happened at the company. We only learn about those when we cross-check with HR.

Keeping people for a second year is better for the plant than bringing new ones: no new recruitment, D visas, consulates or first weeks of processing. But that advantage disappears if even one extension window closes unnoticed. For that person everything starts again: a new permit, a new fee, a new entry. That's why we run extensions as a separate project with its own plan, not as a routine application.

Illustrative photo. Before an extension we check every file, not just the dates.

An extension doesn't start with an application. It starts with the question: what has changed in a year?

02 / The inventory

Twenty-two sets of documents on a single sheet

The cross-check took a week: HR provided the staffing schedule, transfer orders and contracts, and the workers provided passports and residence cards. We recorded every discrepancy on a separate line, because discrepancies are exactly what gets an application left without motion or refused.

The findings fell into four groups. Most people were extending with no changes. But two operators had a new job title, one packer had a new passport, and all twenty-two had been living in the plant's new dormitory since March.

Vikram, a packer, got a new passport at the consulate in winter. The permit update was filed on time then, and in the cross-check we confirmed that the extension application already carried his new passport details. How we handle a new passport mid-contract is covered in the scenario about a trip home. One more detail: two workers from the first wave agreed to a two-year contract, the rest to one year. On extension the permit term follows the new contract, so their applications differed.

Cross-check results before extension
GroupPeopleWhat changedWhat we do
No changes18Nothing but the termExtension application on the first day of the window
Transferred to another job2Job title and contractPermit update first, then extension
New passport1Passport detailsCheck the update was filed on time
New dormitory address22Registered addressDocuments for the new building for residence permits

03 / The window

Why the application goes in on the first day, not the last

The Employment Law allows a permit extension application no earlier than 50 and no later than 20 calendar days before the term ends. An application outside that window is a separate ground for refusal, and it can't be fixed: a new permit would have to be obtained from scratch.

So each wave has not one date in the register but three: the window opening, our internal deadline on day five of the window, and the window closing. We prepare applications in advance and file in the first days. If an application is left without motion, the law gives three working days to correct it, and filing on day one means we can fix everything long before the window closes.

An extension needs an application, a photo and documents on any changes. The company pays the extension fee from its own account, and it's one subsistence minimum less than the fee for issuing a permit for the same term. We sent the invoices to the plant's accounts department a week before the window opened so payment wouldn't delay filing. For the two workers on two-year contracts the fee is higher, and we showed the plant that on a separate line before the contracts were signed.

  1. 60 days before end

    Request to HR: second-year contracts, photos, orders on any changes.

  2. 55 days

    Fee invoices to accounts, applications ready to file.

  3. 50 days

    The window opens. We file for the first wave.

  4. Within 3 working days

    Decision. The plant and each worker receive copies.

  5. 20 days

    The window closes. By then every decision is already in hand.

04 / Job titles

Two operators promoted mid-year

In spring the plant moved two packers up to line operator. For the plant it's an ordinary HR decision; for the documents it means a mandatory update to the work permit. The law requires filing it within 30 days of the transfer, with a new version of the contract or a supplementary agreement.

In the cross-check we saw the transfer order had been signed but no permit update filed: HR assumed it would be done with the extension. There was a week left of the 30 days. We prepared the update applications in two days, the plant signed supplementary agreements, and the updates were filed on time. A decision is made within three working days, and updates are free.

Only then did we file extensions for those two. Had we extended on the old job title, the permit would describe work the person no longer does, and working on terms other than those in the permit means a fine for the employer for each worker.

05 / The address

A new dormitory and documents that didn't exist yet

In March the plant moved all workers from a rented dormitory into its own renovated building. People moved over a weekend, but HR hadn't yet gathered documents for the new address for registration of residence or for residence permit extensions.

We checked the new building the way we check any address before filing: the plant's ownership, the building's designated use, and whether the company can provide documents to register twenty-two people. One document was missing, and the plant obtained it in three weeks. That's exactly why we started the cross-check two months ahead rather than a week before the window.

Once the address documents were ready, we updated the registration of residence for all twenty-two and only then set dates for residence permit extension filings. That way the applications carried the address where people actually live.

  1. 01

    Ownership

    A document showing the building belongs to the plant or the plant has the right to house people in it.

  2. 02

    Designated use

    The building is fit for living in, not registered as a warehouse or office.

  3. 03

    Capacity

    The documents allow all workers to be registered at the address.

  4. 04

    Term

    The right of use covers the whole term of the extended permit.

06 / Residence permits

Twenty-two in-person filings without queues or downtime

After the permits are extended, each worker must file in person to extend their temporary residence permit. Twenty-two people on one day means a full day of queuing and half the shop without operators. So we split the filings into groups of four or five and agreed with the plant on the days their absence would be least noticeable.

Rajesh, our manager for workers from India, went with every group: he checked documents on the bus, explained in Hindi what would happen during filing, and made sure nobody forgot a passport or old card. Each group was back at the plant by lunchtime. Before the first group we re-checked the old cards' dates: none expired before the person could file, so the lines, not the deadlines, set the order of the groups. Whoever's card expired soonest went in the first group.

  • each group is made up of people from one line, so no line loses more than two operators in a day;
  • the day before filing, everyone gets a document list in their own language;
  • Rajesh carries copies of the whole group's documents in case of questions;
  • we enter the new cards' issue date in the register and inform the plant;
  • the new residence permit end date goes into the register the same day.

07 / The register

What's in the register now for year three

After the extensions, the date register was updated for all twenty-two: new permit end dates, new residence permits, the dates of the next extension windows. WORKIN's documents department and the plant's HR both have access, so dates don't depend on any single person. Once a month Nataliia sends the plant a short report: what's changed and which deadlines are approaching. How we keep such a register through migration support is described on the service page, and what's the company's own responsibility is on the employer duties page.

Together with the plant we agreed on three signals that HR reports to us the same day: a transfer order, a worker's new passport and any change of address. Each starts its own deadline, and missing one costs more than an email. What to do when an application does get left without motion is covered in the scenario about an application left without motion, and how to update permits after a company is renamed in the scenario about updates after a reorganisation.

Illustrative photo. People keep working, and the second-year documents are already in order.

08 / Outcome

The second year began without a single day of work without documents

Extensions
22 permits extended, applications filed in the first week of the window
Job titles
Updates for two operators filed within 30 days, before the extension
Passport
Update after the new passport checked, permit details current
Address
Documents for the new dormitory gathered, registration updated for everyone
Residence permits
In-person filings in groups, with no lines stopped

There's nothing in second-year documents that WORKIN can't solve: we see windows, transfers, new passports and new addresses coming and deal with them before they become a problem. If any worker decides not to stay, the WORKIN replacement guarantee applies: at least 6 months from the worker's first shift, provided the agreed working, pay and housing conditions are kept. You can estimate permit and extension costs for your headcount in the calculator. More on such projects on our pages about workers for manufacturing and workers from India.

09 / FAQ

Questions and answers

When should a work permit extension be filed?

No earlier than 50 and no later than 20 calendar days before the permit ends. We file in the first days of the window to leave room for corrections.

What happens if an extension is filed late?

Filing outside the deadline is a ground for refusing the extension. A new permit then has to be obtained, which is why we track the date in the register.

How much does a permit extension cost?

The fee is one subsistence minimum for able-bodied persons less than the fee for issuing a permit for the same term. The employer pays it from its own account.

What if a foreign worker is transferred to another job?

File a permit update within 30 days of the transfer, with a new version of the contract or a supplementary agreement. Updates are free.

Does the worker need to be present for a permit extension?

No, the employer or WORKIN files under a power of attorney. The worker files in person to extend the residence permit.

What if the company moves workers to a new address?

Gather documents for the new building, update the registration of residence, and only then file residence permit extensions with the new address.

For how long can a permit be extended?

For employees, for the term of the employment contract but no more than two years. The employer may specify a shorter term.

How this material was prepared

Author
Nataliia Kravchuk, Head of Documents at WORKIN
Rules last checked
September 2026
Sources
Law of Ukraine on Employment of the Population, WORKIN control-date register and worker guide
Method
the scenario is built from typical situations in our work; extension and update deadlines and fees are checked against the Employment Law, and practical steps come from WORKIN documents

Sources and methodology

  1. [1]

    Law of Ukraine on Employment of the Population No. 5067-VI

    Articles 42-3, 42-4, 42-5, 42-6, 42-7, 42-9: permit term, fees, updates, decision times, extension window, refusal

    zakon.rada.gov.ua

Rules checked against the official text as of September 2026. Address document requirements for registration are checked before every filing.

About the author

Nataliia Kravchuk

Author: Nataliia Kravchuk

دستاویزات کے شعبے کی سربراہ

Heads the documents department: permits, visas, residence permits, extensions and updates for foreign workers on every WORKIN project.

Focus
Permits, visas, residence permits and deadlines for foreign workers
Responsibility
Documents from request to permit extension

Related materials

What to read next

Typical scenarios

Similar situations at other plants

Documents

Foreign workers staying a second year?

We'll check every worker's documents, file extensions in the first days of the window and handle updates, addresses and residence permits without downtime.

Get a consultation →